Dear FNL Tenants, Users, and Stakeholders,
Early this fall the Airport will begin work to complete a pavement preservation and improvement project. The project will include crack sealing, seal coating, and repainting of all of the pavements inside the fenced property of the Airport.
This work will require rolling closures of the pavements restricting access to and from hangar facilities and runways and taxiways. Work is scheduled to begin September 25th and extend through mid-October.
The Airport’s runways and taxiways are scheduled to be closed for five days beginning on Sunday, October 1st at 12:00pm, through Friday, October 6th at 12:00pm for crack seal, seal coating, and painting. NOTAMs will be issued for the closures.
The week of October 9th has crack filling and seal coat operations starting in the hangar and apron areas, beginning with the pavements north and working south through the hangar and apron areas. The exact dates and areas of closures will be provided the week prior to the start of the project:
Once active, the website will have daily updates to keep the information accurate and complete.
I wish to extend my appreciation for your cooperation during this time. As with any project, we realize that some issues may arise and we will work to keep everyone informed on any changes and project progress.
|
|